El gráfico muestra el vasto alcance del parque eólico y cómo se conecta con la red eléctrica nacional de Kenia.
GN38224ES

AMBIENTE

El Proyecto de Energía Eólica de Lago Turkana está listo para la producción

August 31, 2018 - El muy pospuesto Proyecto de Energía Eólica de Lago Turkana, en Kenia, situado al pie del Monte Kulal, suministrará electricidad de bajo costo a la red nacional. La planta masiva de energía constituye la mayor inversión en un proyecto individual en la historia de Kenia, con un costo aproximado de $680m. Sus 365 aerogeneradores suministrarán 310MW de electricidad confiable, suficientes para abastecer un millón de hogares.

The government of Kenya expects construction of the Lake Turkana Wind Power Station to be completed by the end of August 2018, and that delivery of low cost electricity to the national grid will commence in September.

The project has been held up by the government component, a 428km transmission line to connect the Lake Turkana Wind Power project to the national grid. This has suffered numerous delays, ranging from land management issues with local communities to a key contractor filing for bankruptcy.

The Lake Turkana Wind Power project boasts 365 wind turbines, each with a capacity of 850kW. It will produce a total of 310MW electricity generation capacity, or 15 per cent of Kenya’s installed capacity at present.

The east African nation relies heavily on renewables such as geothermal and hydro power for its electricity supply and is investing in increasing electricity generation to keep up with growing demand for power and to reduce frequent blackouts.

Sources
PUBLISHED: 07/08/2018; STORY: Graphic News; PICTURES: Vestas (handout)